Clearance of Husainpur Drain From KM 0.000 to 5.430 for Year 2026-27
₹2.38 Lakh
Item Rate₹5,000
Fixed₹589
Payable15 Days
Execution TimelineTender Details
Work Description
Bidders & 5-Stage Evaluation Intelligence
12 May 2026, 10:00 am
Closed 18 May 2026, 10:00 am
3 bids recorded • 1 qualified
2 ranked • L1 ranked
M/S RATHAUR CONTRACTOR
Financial Evaluation & L1 Contractor Ranking
| Rank | Contractor / Firm Name | Quoted Bid (₹) | Variance vs Estimate | Portal Status | Committee Remarks | Action |
|---|---|---|---|---|---|---|
| L1 | M/S RATHAUR CONTRACTOR↗ Bid ID: 6121782•Submitted: 17-May-2026 12:47 PM | ₹2.02 L | -15.31% ₹-36,430.87 | Accepted-AOC | Lowest Bidder | Profile ↗ |
| L2 | DREAM WORLD DEVELOPMENT CONSTRUCTION↗ Bid ID: 6121847•Submitted: 17-May-2026 01:24 PM | ₹2.38 L | +0.17% ₹415.1 | Rejected-Finance | - | Profile ↗ |
Technical Cover Scrutiny Results (3)
Statutory credential compliance verification by the departmental scrutiny committee
| # | Bid ID | Contractor Name | Submitted Date | Technical Status | Disqualification / Remarks | Portal Status | Profile |
|---|---|---|---|---|---|---|---|
| 1 | 6121847 | DREAM WORLD DEVELOPMENT CONSTRUCTION | 17-May-2026 01:24 PM | ✕ DISQUALIFIED | L2 | Rejected-Finance | Dossier ↗ |
| 2 | 6123495 | M/S MAMTA KASHYAP CONTRACTORS | 18-May-2026 09:06 AM | ✕ DISQUALIFIED | LOT NUMBER FILLED INCORRECTLY IN THE IDT-3 | Rejected-Technical | Dossier ↗ |
| 3 | 6121782 | M/S RATHAUR CONTRACTOR | 17-May-2026 12:47 PM | ✓ QUALIFIED | Credentials verified per NIT specifications | Accepted-AOC | Dossier ↗ |
Tender Document & BOQ Analysis
Itemised work schedule, qualification criteria, and bid pricing scenarios
Tender Documents & Itemised BOQ Protected
Sign in or create a free Contracq account to download the official tender notice (NIT), standard bidding documents (SBD), and itemised bill of quantities (.xls).
Work Site Location & Geospatial Map
AI Bid Viability & Projected EPC Margin
Normative cost breakdown, risk index, and contractor margin sensitivity modeling
AI Bid Viability & Projected EPC Margin Protected
Unlock predictive cost breakdowns, normative CPWD/MoRTH sensitivity models, risk indexes, and contractor bid margin predictions for this tender.